A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
Correct Answer: B
In an agile environment, accountability is achieved through transparency, collaboration, and shared understanding of the project's goals and objectives. The agile model emphasizes the importance of open communication and collective responsibility among team members. By fostering an environment where the marketing vice president and other stakeholders can openly discuss issues and agree on objectives, the project manager ensures that everyone is aligned and accountable for the project's success. This approach aligns with the principles of both Agile and Business Analysis, which advocate for stakeholder engagement and collaborative decision-making to deliver value and meet business needs. References: (Agile Methodology in Project Management as a Licensed PMP1, Accountability is a Quality of Agile2, Professional in Business Analysis Certification | PMI3, What is Personal accountability? - The Functional BA4)