Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone. What should the project manager do first?
Correct Answer: B
When a delay occurs, it is essential for the project manager to engage with the team to understand the reasons behind the delay. This approach aligns with the principles of both Project Management and Business Analysis, where communication and problem-solving are key to addressing project challenges. By discussing the issue with the team, the project manager can gather insights into the root causes of the delay and work collaboratively to find a solution that minimizes the impact on the project milestone. This method is preferred over immediately seeking assistance from senior management or reallocating resources, which may be more disruptive and less informed actions at this stage. References: = The approach of discussing delays with the team is supported by the PMI's guidance on dealing with project delays, which emphasizes the importance of understanding the causes of delays and working with the team to resolve them1. Additionally, the Professional in Business Analysis materials highlight the significance of stakeholder engagement and communication in managing project challenges2.