The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected. What should the project leader do?
Correct Answer: B
In Agile project management, when a team member is struggling with an impediment that is hindering the team's progress, the project leader should identify the impediment and associated risks at the daily standup12. The daily standup, also known as the daily scrum, is a short meeting where the team discusses progress and identifies obstacles2. By bringing up the impediment and its associated risks during this meeting, the project leader ensures that the entire team is aware of the issue and can work together to find a solution12. This approach aligns with the Agile principle of self-organization, where individuals on the team take on key responsibilities2. References: * Who Is An Agile Team Leader And What They Do?1 * Agile Team Roles and Responsibilities: A Brief Guide2 * Leadership in agile projects - what makes for success?3