An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this knowledge in the future. What should the agile project manager do?
Correct Answer: B
In agile project management, knowledge sharing is crucial for the team's collective growth and adaptability. When a team member develops expertise in a specific area, it is beneficial for the agile project manager to encourage that individual to share their knowledge with the rest of the team. This can be done effectively through a training session, which not only disseminates the knowledge but also fosters collaboration and learning within the team. This approach aligns with the principles of agile methodologies, which emphasize team interaction, continuous improvement, and responding to change12. References: * PMI's "Managing Project Management Knowledge" article1. * LinkedIn's "How to Lead and Empower Your Project Team with PMBOK" article2.