In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
Correct Answer: C
In a project, when a task on the critical path is at risk of delaying the schedule, it's crucial for the project manager to identify any impediments that might be causing the delay. In Agile methodologies, such as Scrum, this is often done during daily standup meetings. If a team member has been providing the same update for several days, it may indicate that they are facing a blocker. The project manager should ask the team member if there is an impediment and help to remove the blockers. This approach promotes problem-solving and helps keep the project on track. References: PMBOK Guide, 6th Edition, Section 8.3 - Control Schedule