During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
Correct Answer: D
When facing difficulties in communication with a stakeholder, it is advisable to revisit and update the stakeholder engagement plan. This ensures that the approach to stakeholder engagement is tailored to their specific communication needs and preferences, which may increase the likelihood of successful interaction and feedback. The PMI standards advocate for the continuous monitoring and adjusting of stakeholder engagement activities to address and manage individual stakeholder requirements effectively. References: = The PMI's "A Guide to the Project Management Body of Knowledge (PMBOKGuide)" and "Business Analysis for Practitioners: A Practice Guide" both provide guidance on stakeholder engagement and the importance of adapting communication strategies to meet the needs of different stakeholders12.