A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?
Correct Answer: C
The project manager should address the issue between the two team members by scheduling a meeting with them and using conflict resolution techniques to find a mutually acceptable solution. This way, the project manager can prevent the issue from escalating and affecting the project performance and team morale. This approach is consistent with the agile principle of fostering collaboration and trust among the team members12. References: 1: PMBOK Guide, 6th Edition, Chapter 9: Project Resource Management 2: Agile Practice Guide, Chapter 2: An Agile Mindset