A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration. What should the project lead do?
Correct Answer: D
When faced with a new regulatory feature that exceeds the capacity of the remaining iteration, the project lead should take the following steps: 1.Estimate the Impact: The project lead should assess the impact of incorporating the new feature. This involves evaluating how it affects the project timeline, resources, and overall project goals. 2.Consult with the Product Owner: The project lead should engage with the product owner to discuss the feasibility of accommodating the new feature within the existing iteration. The product owner can provide insights into the importance of the feature, potential trade-offs, and whether it aligns with project priorities. 3.Consider Trade-offs: If the new feature significantly impacts the iteration, the project lead may need to make trade-offs. This could involve adjusting other features