A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities. What should the project manager do?
Correct Answer: C
In a functional organizational structure, departments such as purchasing operate independently and are managed by their respective department heads12. When project tasks are delayed due to other priorities within a department, it is essential for the project manager to engage directly with the department causing the delay-in this case, the purchasing department. By meeting with the purchasing manager, the project manager can discuss the importance of the project's tasks, understand the reasons for the delay, and work collaboratively to establish a purchasing schedule that aligns with the project's needs while respecting the department's constraints345. This approach fosters communication and collaboration, which are key in a functional structure where the project manager has limited authority over departmental resources. References: = The role of the project manager in a functional organizational structure and the importance of direct communication with department heads to resolve delays and align schedules are well-documented in project management literature12345.