The project sponsor on an agile project informed the project lead that an executive would like an update on the project's progress What should the project lead do?
Correct Answer: B
According to the PMBOK Guide, 7th edition, section 14.2.2, "Information radiators are highly visible displays of project information that are easily accessible and frequently updated. They are used to communicate project status and progress to the project team and other stakeholders, especially in agile or hybrid approaches." Therefore, the project lead should invite the executive to the project's meeting space to determine if the project information radiators meet their needs, as this is the most effective and transparent way to provide an update on the project's progress in an agile environment. Providing a link to the project's shared drive for the executive to search through for any artifacts that are of interest (option A) may not be user-friendly or efficient, as the executive may not know what to look for or how to interpret the artifacts. Reaching out to the PMO for status report templates and providing project updates in that format (option C) may not be aligned with the agile principles or values, as it may introduce unnecessary documentation or bureaucracy. Asking the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments (option D) may not be appropriate or respectful, as the project lead should also be responsible for communicating with the stakeholders and ensuring their satisfaction. References: * PMBOK Guide, 7th edition, section 14.2.2 * PMI-PBA Exam Practice Test and Study Guide, 2nd edition, page 183, question 20