During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register. Which project document should the project manager review in order to determine the reason for this issue?
Correct Answer: C
The Stakeholder Engagement Assessment Matrix is a tool used to identify the current and desired levels of stakeholder engagement throughout a project. It helps project managers to monitor and compare the expected engagement and involvement of stakeholders against actual engagement. If a major stakeholder is unaware of recent developments, it suggests there may be a gap in the desired and actual engagement levels, which this matrix is designed to track and highlight. References: = The information is aligned with the PMBOKGuide, which outlines the importance of stakeholder engagement and the use of the Stakeholder Engagement Assessment Matrix as a tool to manage and assess this engagement12. Additionally, the PMI's standards for project management emphasize the need for effective communication and engagement with stakeholders to ensure project success34.