A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?
Correct Answer: A
In an agile project management context, the scope is not fixed but is regularly reviewed and adapted based on stakeholder feedback and project progress12. The project manager should facilitate collaboration among sponsors, stakeholders, and the team to ensure a shared understanding of the product vision and to clarify expectations3. This approach aligns with the agile principle of welcoming changing requirements and focusing on customer collaboration over contract negotiation1. References: * "What Is Agile Project Management? | A Comprehensive Guide"1. * "What is Scope Management in Agile Project Management - BVOP"2. * "Iron Triangle Project Management | Atlassian"3.