At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried to contact the consultant but has been told that the consultant does not have the time to discuss the project. What should the project manager do to move the project forward?
Correct Answer: C
In project management, effective communication and stakeholder engagement are crucial. When a business analyst requires input from a marketing consultant, it is the project manager's responsibility to facilitate this interaction to ensure project tasks can continue. The project manager should actively engage with the consultant to understand their constraints and schedule a dedicated time for discussion that aligns with the project needs1. This approach ensures that the project moves forward without unnecessary delays and maintains a collaborative environment. References: * "4 Techniques to Facilitate Effective Project Meetings" - Project Management Institute1.