A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project. How should the project manager resolve this situation in their new role as servant leader?
Correct Answer: D
In an agile approach, the team is self-organizing and empowered to make decisions. The product owner should not be defining sprint backlog items that cannot be delivered within the agreed sprint duration. Instead, the team should work together to define the sprint backlog items based on the product backlog items prioritized by the product owner. If the increments do not meet the acceptance criteria, the team should work with the product owner to understand the criteria and ensure they are met in future sprints. The servant leader's role is to facilitate this process and help the team become more effective. References: Agile Practice Guide from www.pmi.org and A Guide to the Project Management Body of Knowledge (PMBOK Guide) from www.pmi.org.