A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person What should the project manager do first?
Correct Answer: B
The Work Breakdown Structure (WBS) is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body of Knowledge (PMBOK) defines the work breakdown structure as a "deliverable oriented hierarchical decomposition of the work to be executed by the project team." This option is the most effective way to manage large and complex deliverables that cannot be assigned to a single person. References: PMBOK Guide, 6th Edition, Section 5.4: Create WBS