Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high performer, the project goals may be negatively impacted if they leave the team. What should the project manager do in this situation?
Correct Answer: B
The best approach in this situation is for the project manager to meet with the team members and the developer individually to understand the underlying issues and perspectives. This aligns with the conflict resolution strategies outlined in the PMBOK Guide, which emphasizes the importance of addressing conflicts proactively and collaboratively12. By meeting with the parties involved separately, the project manager can gather unbiased information, which is crucial for formulating an effective action plan. This approach also allows for a more personalized discussion, where each individual can express their concerns without the pressure of group dynamics. Once the project manager has a clear understanding of the conflict's root causes, they can work with the team to develop a resolution strategy that addresses the concerns of all parties and supports the project's goals. References: The PMBOK Guide and materials on conflict resolution techniques for project management professionals, as well as best practices for business analysts in managing conflicts123.