A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year Which project approach suits the scenario?
Correct Answer: A
According to the PMBOK Guide, a Scrum project is an example of an adaptive or agile approach that is suitable for projects with high uncertainty, changing requirements, and fast delivery. A Scrum project delivers value incrementally through short iterations called sprints, where the team collaborates with the customer and other stakeholders to define and prioritize the product backlog, which contains the features and functionalities of the product. The team then selects a subset of the product backlog items to work on during each sprint, and delivers a potentially shippable product increment at the end of each sprint. The team also inspects and adapts the product and the process through frequent feedback loops and retrospectives. Therefore, a Scrum project suits the scenario of a new product launch with evolving requirements and flexible scope, as it allows the team to start the work based on the forecast of a similar project, but also to respond to changes and customer needs as they emerge. References:
* PMBOK Guide, Chapter 2, Section 2.4.2, Adaptive Life Cycle
* PMBOK Guide, Chapter 13, Section 13.2.2.1, Agile/Adaptive Environments
* PMBOK Guide, Appendix X3, Section X3.2, Agile Principles
* Agile Practice Guide, Chapter 2, Section 2.2.1, Scrum
* Agile Practice Guide, Chapter 3, Section 3.2, Delivering in an Agile Environment