In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
Correct Answer: A
In an agile project, when there is a disagreement about a major new requirement among key stakeholders, the project manager should facilitate a meeting with the stakeholders and product owner to clarify the new need. This approach ensures that all parties have a clear understanding of the requirement and can work towards a common goal. It also helps to prevent potential issues that could arise from misunderstandings or miscommunications. References: PMBOKGuide - Sixth Edition, Section 13.2.2.1: Plan Stakeholder Engagement