A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
Correct Answer: D
In an agile project, collaboration and team input are crucial for success. Before sending details and estimates to the client, the project manager should engage with the team to gather their insights and expertise. This ensures that the project plan reflects a realistic approach, considering the team's views on dependencies and potential risks. Agile methodologies emphasize the importance of team collaboration and iterative development, which includes regularly revisiting and adjusting plans as the project progresses1234. References: * Agile Communication: Techniques, Examples and Best Practices1 * How to Nail Your Agile Communication Plan2 * How to Communicate and Collaborate with Stakeholders in Agile Projects3 * The Agile Project Management Approach4