A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers. What should the project manager do?
Correct Answer: B
The role of the Scrum Master includes removing impediments to the Developers' progress. This is a key responsibility as it enables the team to work efficiently and deliver high-quality products. When a complaint arises regarding the Scrum Master not removing impediments, it is important for the project manager to clarify and agree on what constitutes an impediment that the Scrum Master should address. This ensures that there is a shared understanding of the Scrum Master's responsibilities and helps prevent future delays caused by unresolved impediments1234. References: Scrum.org, DeepProjectManager.com, LinkedIn, PremierAgile