A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up. What should the project manager do?
Correct Answer: B
Agile methodologies encourage teams to continuously inspect and adapt their methods to improve efficiency and effectiveness. If a team member suggests a new estimation method because the current method is causing difficulties, it would be beneficial for the project manager to review this method with the entire team. This allows the team to discuss the pros and cons of the new method and make a collective decision on whether to adopt it. References: Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide)-Seventh Edition. Project Management Institute.