During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal impact on project resources. However, the client has only been focused on the next milestone. How should the project manager approach this situation?
Correct Answer: C
In this scenario, the project manager should review the change management plan to discuss the potential early benefits realization with the client. This involves evaluating the impact of the change, considering the client's focus on the next milestone, and discussing how the early completion of a deliverable could bring value to the project without significantly affecting resources. The goal is to align the project's progress with the client's expectations and the project's objectives, ensuring that any changes are beneficial and agreed upon by all stakeholders. References: The answer is based on the principles of engaging stakeholders and managing changes effectively as per the PMP and PMI-PBA guidelines1234.