Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations. What should the project manager do next to address this issue?
Correct Answer: C
In the face of travel restrictions, the project manager should encourage team members to continue their work independently while exploring needs and alternatives. This approach aligns with the PMBOKGuide's emphasis on project communications management, which includes ensuring that there is an effective plan to communicate project information to stakeholders and team members to achieve project objectives1. It also reflects the PMP's focus on adaptive project environments where project teams must be able to respond to changes and continue to work towards project goals2. References: * PMBOKGuide - Seventh Edition1 * PMP Examination Content Outline - June 20192 * Professional in Business Analysis Reference Materials3