From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
Correct Answer: C
The project manager should work with the client on an acceptable amount of time for document approval, as this is the best way to address the issue of slow turn-around times and avoid potential delays in the new project. By collaborating with the client, the project manager can establish a mutual understanding of the expectations, requirements, and constraints of the document approval process, and negotiate a realistic and feasible timeline that satisfies both parties. This will also help the project manager to build trust and rapport with the client, and foster a positive and cooperative relationship.