A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty What should the project manager have done to avoid this situation?
Correct Answer: A
The project charter is a document that authorizes the project and defines its objectives, scope, stakeholders, and high-level risks. It also includes the project management approach and the roles and responsibilities of the project team. The project charter should be distributed to all team members and other key stakeholders to ensure their awareness and alignment with the project vision and expectations. The project charter also contains the project ground rules, which are the agreed-upon norms and behaviors that guide the team's interactions and collaboration. The ground rules should be clear, specific, measurable, and enforceable. They should also be reviewed and updated periodically to reflect any changes in the project environment or team dynamics. By distributing the project charter to all team members, the project manager can avoid misunderstandings, conflicts, and disagreements regarding the project ground rules and the consequences of violating them. References: PMBOK Guide, 6th edition, section 4.1.3.1; PMP Exam Prep, 10th edition, page 93