A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market. What should the project manager do to move forward with the project?
Correct Answer: D
In this scenario, the project manager should engage with all stakeholders, including the farmers' group, to discuss the project objectives and review their requirements. This is in line with the best practices of stakeholder engagement and management, which are critical for the success of any project. By involving the farmers' group, the project manager can understand their needs and concerns, and work towards a solution that accommodates all parties involved. This approach not only helps in mitigating risks but also ensures that the project delivers value to all stakeholders. References: = The importance of stakeholder engagement is highlighted in PMI's resources on project management and business analysis. Engaging stakeholders for project success is a key aspect of the PMI's guidance on project management1. Additionally, the role of business analysts in gathering stakeholder requirements and ensuring that projects deliver the expected business benefit is emphasized in PMI's Professional in Business Analysis materials2.