Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:

Access PMP Dumps Premium Version
(1975 Q&As Dumps, 35%OFF Special Discount Code: freecram)

Online Access Free PMP Exam Questions

Exam Code:PMP
Exam Name:Project Management Professional (2025 Version)
Certification Provider:PMI
Free Question Number:336
Version:v2020-10-30
Rating:
# of views:2065
# of Questions views:106207
Go To PMP Questions

Recent Comments (The most recent comments are at the top.)

Nancy - Jun 27, 2024

Best pdf exam dumps for PMP exam. I was able to score 90% marks in the exam with the help of content by freecram. Many thanks to freecram.

Hulda - Aug 03, 2022

I am your loyal customer, perfect PMI as before.

Hiram - Jun 05, 2022

Though the PMP exam file has some questions double submitted and correct answer errors, it is still enough to pass. And i passed it with about 91%. Great!

Maria - May 24, 2022

These PMP practice test questions are out of this world. They are specific to the objectives of the exam and thoroughly they give you what you require to pass your exam. By using them recently as part of my revision, i went through my exam without fear and passed. Thanks!

Phoebe - Dec 24, 2021

You can choose to use this PMP learning dumps for your revision. I have an good experience with their practice tests and passed my PMP exam easily. It is the best way to pass your exam.

Harry - Dec 19, 2021

I passed PMP because it is important in my job and studied hard and passed.

Erin - Dec 18, 2021

I just passed my PMP exam, thank you so much! freecram, you are the best!

Berger - Nov 26, 2021

The PMP exam file i got was very useful. They gave me the much needed boost in passing my PMP exam!

Abraham - Sep 22, 2021

I was attempting my PMP exam the second time, and my friend advised me to get this PMP practice test. I passed very well.

Janet - Aug 23, 2021

Thank you so much for your support. It was a great helper. I passed the PMP exam this monday.

Constance - Jun 15, 2021

freecram is 100% guaranteed! I got success in PMP Certification exams which I prepared by this site.

Ada - May 25, 2021

I practiced the PMP question sets for days and then i passed the exam last week with highest marks-full marks.

Tommy - Nov 30, 2020

No.# This answer should be B.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
3301 viewsPMI.PMP.v2024-08-26.q776
2233 viewsPMI.PMP.v2024-07-03.q171
1335 viewsPMI.PMP.v2024-05-21.q498
2990 viewsPMI.PMP.v2023-10-10.q253
10724 viewsPMI.PMP.v2022-07-17.q478
6614 viewsPMI.PMP.v2022-04-02.q436
3111 viewsPMI.PMP.v2022-03-01.q365
2194 viewsPMI.PMP.v2022-02-28.q231
2910 viewsPMI.PMP.v2022-02-01.q251
3074 viewsPMI.PMP.v2021-11-23.q161
3220 viewsPMI.PMP.v2021-11-17.q210
4834 viewsPMI.PMP.v2021-08-21.q133
2241 viewsPMI.PMP.v2021-06-27.q182
2706 viewsPMI.PMP.v2021-05-06.q96
2254 viewsPMI.PMP.v2021-05-04.q62
1843 viewsPMI.PMP.v2021-04-21.q138
1952 viewsPMI.PMP.v2021-03-29.q180
1940 viewsPMI.PMP.v2020-12-20.q134
2402 viewsPMI.PMP.v2020-10-04.q300
2076 viewsPMI.PMP.v2020-09-10.q255
2547 viewsPMI.PMP.v2020-08-14.q299
2182 viewsPMI.PMP.v2020-06-11.q185
2150 viewsPMI.PMP.v2019-05-17.q1011
1833 viewsPMI.pmp.v2018-11-12.q1030
1961 viewsPMI.PMP.v2018-04-10.q900
3413 viewsPMI.PMP.v2017-12-15.q3515
Exam Question List
Question 1: A project manager is performing a set of processes in the In...
Question 2: A project manager is running a long-term project for a compa...
Question 3: As part of the Risk Response planning for your project, you ...
Question 4: Despite the project manager's continual reminders about the ...
Question 5: A project manager is in the process of determining, document...
Question 6: A project manager is having difficulty obtaining resources f...
Question 7: ZULFI is the Project Manager of a new product development pr...
Question 8: You are managing a social health insurance project. You are ...
Question 9: A project team member identifies a simple change that will i...
Question 10: A project manager invites stakeholders to a lessons learned ...
Question 11: During a protect status meeting, the project manager identif...
Question 12: An audit was conducted on a project during close out The iss...
Question 13: A change to a project's scope demotes was verbally approved ...
Question 14: One of the tasks to be completed before the start of the pro...
Question 15: During a project's execution phase, a developer suggests a d...
Question 16: You are a project manager working on a large construction pr...
Question 17: Midway through the design phase of a software development pr...
Question 18: During an IT solution implementation project, the project ma...
Question 19: An ongoing cross-functional project has team members located...
Question 20: A project manager discovers a significant flaw in a major pr...
Question 21: The project manager sees that there is a quality issue and t...
Question 22: After several weeks on a new project, the project manager le...
Question 23: A project manager is developing a schedule for a communicati...
Question 24: A new warehouse facility is under construction. The project ...
Question 25: During the construction of a port, a nearby fishing communit...
Question 26: Carlos is managing a software development project. There was...
Question 27: As a project manager for a construction project, you underst...
Question 28: To implement a customer relationship management (CRM) softwa...
Question 29: The product owner notifies the project manager about a risk ...
1 commentQuestion 30: A project is three weeks behind schedule and the baseline fi...
Question 31: A project manager receives an approved change request relate...
Question 32: An organization has contracts with an external supplier to s...
Question 33: A new project manager has been appointed in the middle of a ...
Question 34: A new project manager joins a project in its execution phase...
Question 35: Phase two of a complex, multi-phase project is completed, an...
Question 36: A project team member decides that engaging the customer on ...
Question 37: A project manager is working on a project that will result i...
Question 38: As a project approaches its final phase, the project manager...
Question 39: A key project stakeholder and influencer has suddenly withdr...
Question 40: During a portfolio review meeting, a project manager teams t...
Question 41: During project charter development, a stakeholder notices th...
Question 42: Due to recent organizational changes, a number of project st...
Question 43: A project manager in a weak matrix organization notices that...
Question 44: Provisional training is provided for a project that is in th...
Question 45: Some company board of director members feel that the organiz...
Question 46: Near the end of a project, the project manager discovers tha...
Question 47: A project manager has just started planning his project. If ...
Question 48: A project is experiencing issues that affect the project cos...
Question 49: During a project the project manager realizes that a special...
Question 50: A stakeholder with a high degree of impact now requires more...
Question 51: A project manager expected a vendor to complete testing of e...
Question 52: Sensitivity analysis helps to determine which risks might ha...
Question 53: An approved change request adds an incentive to a lump sum c...
Question 54: A project that uses several vendors is estimated to complete...
Question 55: A project manager is assigned to a project that is in progre...
Question 56: A project manager is in the planning stage of a new software...
Question 57: A project management has concluded the review and approval p...
Question 58: You are a project manager working on a software development ...
Question 59: A project manage identifies the root cause of a quality issu...
Question 60: During a crisis, additional resources and time were required...
Question 61: The purpose of the project charter is:...
Question 62: While reviewing a status report, a project manager notices t...
Question 63: A project manager is working on a project to create a new so...
Question 64: During a project meeting, a junior engineer escalates a tech...
Question 65: The project manager of a large software implementation proje...
Question 66: A key stakeholder misses a project kick-off meeting. The pro...
Question 67: During the construction of a facility project, the project m...
Question 68: A project manager is briefing the sponsor on project progres...
Question 69: You are performing the Perform Qualitative Risk Analysis pro...
Question 70: During project implementation, a project manager discovers t...
Question 71: A concept that is unique to each organization and includes t...
Question 72: During the creation of the project schedule, the project man...
Question 73: A proved is delivered that meets the approved business requi...
Question 74: During the end of a Critical project's execution phase, a pr...
Question 75: A project successfully met its goals on time and all deliver...
Question 76: A project manager is working on a complex project with multi...
Question 77: As a project manager, which tool would you use to bring toge...
Question 78: A project manager needs to add a subject matter expert (SME)...
Question 79: A project manager conducts an inquiry into the increase of s...
Question 80: Based on your success on previous projects, you have been as...
Question 81: A project manager is gathering formal project requirements A...
Question 82: You are a project manager working on a project when the cust...
Question 83: A project manager and project team identify that the number ...
Question 84: A project manager realizes that an issue that occurred sever...
Question 85: You work as a project manager for your company. You have com...
Question 86: Which of the following is a tool to assess the current and d...
Question 87: A project is in the execution phase and product testing is a...
Question 88: A key deliverable requires a specific set of skills and know...
Question 89: A project manager preparing a project status update calculat...
Question 90: A software business partner of a project is delayed in the d...
Question 91: A project manager developed a project management plan for a ...
Question 92: You are developing the project charter for a new project ass...
Question 93: A project manager has two projects of equal, strategic organ...
Question 94: At a status meeting, the customer comments that a main featu...
Question 95: A collection of procedures used to track project artifacts, ...
Question 96: During a projects' planning phase, the high and fluctuating ...
Question 97: Midway through implementation of a construction project, a s...
Question 98: You are a project manager of a large construction project fo...
Question 99: A project manager is in the process of developing the projec...
Question 100: While preparing the resource management plan, a project mana...
Question 101: An organization is awarded a large construction project. The...
Question 102: The contract type that often spans multiple years and allows...
Question 103: All quality controls have passed, and a project deliverable ...
Question 104: During project execution, issues arise because one customer ...
Question 105: You are a buyer-side project manager and have given a contra...
Question 106: A product implementation project has a baseline schedule tha...
Question 107: Outing a weekly review session a key stakeholder rejects a d...
Question 108: An important project stakeholder is replaced, and their succ...
Question 109: A project manager for a 12-month project has a budget of US$...
Question 110: A stakeholder identities an issue with which the project man...
Question 111: A project is on schedule and deliverables are being provided...
Question 112: A company's organizational culture is open engaging and valu...
Question 113: A project manager is using control charts to determine wheth...
Question 114: A project manager delivered the final project report and is ...
Question 115: While reviewing a project management plan for approval, one ...
Question 116: You are managing a design project that would provide design ...
Question 117: A project manager wants to create the risk register. What sh...
Question 118: A project manager has a team of diverse professionals with d...
Question 119: During a kick-off meeting a key stakeholder asks why one of ...
Question 120: A critical resource has resigned, putting a multidisciplinar...
Question 121: After reviewing an approved project's resource management pl...
Question 122: Which risk analysis diagram is used to compare the relative ...
Question 123: A project manager held a cost-benefit analysis workshop with...
Question 124: During a retrospective meeting, the project team discussed t...
Question 125: A company notices that. During the last six projects, the sc...
Question 126: A smooth-running project was meeting schedule and cost basel...
Question 127: This process is concerned with determining the engagement le...
Question 128: During protect execution the project manager notices that th...
Question 129: A project manager needs stakeholder consensus and approval o...
Question 130: After the release of the final project report, a project tea...
Question 131: A project stakeholder requested a scope enhancement that was...
Question 132: At project inception, market demands result in a shift in th...
Question 133: Two members of a project learn are arguing about the specifi...
Question 134: A company's senior manager is expected to supply dedicated r...
Question 135: A project manager is determining the accuracy of the deliver...
Question 136: A project manager has identified project stakeholders, and a...
Question 137: Based on the following table, what are the total float and f...
Question 138: A project has five main sponsors, three of whom often challe...
Question 139: What should the project manager use to compare different sup...
Question 140: Midway through a project, a project manager determined the p...
Question 141: The project manager of a multinational project discovers tha...
Question 142: A project manager is working with a new quality manager to f...
Question 143: A project to implement a new business improvement is initiat...
Question 144: After closing procurements and providing a formal written no...
Question 145: A supplier deliver most of a project's functional requiremen...
Question 146: Mark wants to identify all possible duration and cost outcom...
Question 147: During a project management planning meeting two key stakeho...
Question 148: While preparing a projects third progress report, the projec...
Question 149: A project's most recent status report indicates a schedule p...
Question 150: You are a project manager for a software development project...
Question 151: During a project steering committee meeting, the project man...
Question 152: To estimate the cost of project activities for a new project...
Question 153: A client is requiring the project manager to present on data...
Question 154: A project manager joins a new project that will be implement...
Question 155: A new payment system is being built using agile principles. ...
Question 156: During a progress review of a project near completion, there...
Question 157: A stakeholder requests a change to the project. The project ...
Question 158: After a risk review, the project manager notes an increase i...
Question 159: A project to deliver financial and administrative changes re...
Question 160: A new project manager has just taken over a project. If he w...
Question 161: For the past six months, a project manager has struggled wit...
Question 162: The document that describes how the project scope will be de...
Question 163: During a software development project one team member fails ...
Question 164: An independent, third-party auditor conducted scope verifica...
Question 165: A data center facility was built near a resident community. ...
Question 166: During project execution, a project manager learns that a re...
Question 167: A project is ready to complete the planning process, and all...
Question 168: A project manager reviews the procurement documents and noti...
Question 169: A project status report shows that the earned value (EV) is ...
Question 170: A project manager has finished creating a detailed schedule ...
Question 171: You are managing an IT project in an agile approach. The pro...
Question 172: Which of the following processes groups accept the project d...
Question 173: You are a project manager and you are in the closing phase. ...
Question 174: A customer asks the project manager to deliver a project in ...
Question 175: A project manager meets with the project sponsor and custome...
Question 176: A company has started a drainage improvement project to avoi...
Question 177: A project manager notices that the project is behind schedul...
Question 178: A project manager plans the agenda tor a kick-off meeting. A...
Question 179: Your project is due for a financial review and you have gath...
Question 180: You are a project manager working on a software development ...
Question 181: A project is behind schedule and over budget. As a result of...
Question 182: A project manager assumes a multi-country project that is ex...
Question 183: A project manager assumes a three-year, multiphase project w...
Question 184: The project manager notices that less work was performed tha...
Question 185: You are a project manager, and you are reviewing the deliver...
Question 186: After performing the program evaluation and technique (PERT)...
Question 187: While developing a project's benefits management plan, a pro...
Question 188: A project manager is replaced midway through a very complex ...
Question 189: ZULFI is a project manager who manages equipment installatio...
Question 190: Your project team has just received the sponsor's approval o...
Question 191: You are a project manager working on a project for installin...
Question 192: During a product's testing phase, the customer discovers tha...
Question 193: A project's cost performance index (CPI) is 1.05 and its sch...
Question 194: A project manager learns that the government plans to introd...
Question 195: Stakeholders determine that the business case considers all ...
Question 196: A few weeks after joining a multi-generational project learn...
Question 197: A project sponsor asked a project manager to conduct a benef...
Question 198: The construction process for a building project is complete ...
Question 199: The table lists project activities, with activities A and H ...
Question 200: A senior quality manager complains about a new drone develop...
Question 201: During project execution, the marketing manager stales that ...
Question 202: A project manager wants to communicate project objectives to...
Question 203: A project management team is developing a project management...
Question 204: You are the Project Manager and are currently in the monitor...
Question 205: While reviewing a status report a project manager notices th...
Question 206: During protect execution, a high-performing team member leav...
Question 207: A team is working on a project to address a customer's incom...
Question 208: A project manager is planning a project that has 40 stakehol...
Question 209: During the project initiation phase, the project manager is ...
Question 210: After a steering committee meeting, it is decided that the p...
Question 211: A stakeholder requests a change that will add value to a pro...
Question 212: During a project update meeting, one of the key stakeholders...
Question 213: Which of the following is an output of the Close Projector P...
Question 214: A pipeline project suffered servers storm damage. The perfor...
Question 215: A multinational company with a cross-border project wants to...
Question 216: A project has closed, and the project manager moves on to a ...
Question 217: In the middle of a project, it becomes clear to the project ...
Question 218: You are a project manager who is in charge of an important p...
Question 219: A project sponsor asked the project manager to prepare progr...
Question 220: A customer is surprised about a change made to a deliverable...
Question 221: You're a project manager for a large project. Early on, you ...
Question 222: After stakeholders in a company's sales department examined ...
Question 223: A key stakeholder is concerned about a critical risk that ma...
Question 224: A project manager is working on an assessment project with a...
Question 225: A vendor who supplied material that failed to meet a technic...
Question 226: A project manager identifies a task that will require specia...
Question 227: After approval of a project scope statement, requests for pr...
Question 228: A project manager needs stakeholder approval of the project ...
Question 229: A software company is asked to build an application based on...
Question 230: A project manager discovers an enhancement that will improve...
Question 231: Han way through a project the project manager learns that a ...
Question 232: A project learn member discovered an issue with the system b...
Question 233: Which of the following can the project manager use to group ...
Question 234: A project manager learns there are several unexpected issues...
Question 235: You are working on a warehouse project when you realize that...
Question 236: You are a senior project manager and member of the Project M...
Question 237: A project manager is initiating a highly controversial proje...
Question 238: Two team members are unable to move forward on an activity b...
Question 239: A schedule has two tasks that cannot be started at the same ...
Question 240: While sequencing project activities the team defines that: *...
Question 241: A project team is developing a new enterprise resource plann...
Question 242: Due to organizational changes, a key stakeholder is replaced...
Question 243: The project is currently in the execution phase. During a pr...
Question 244: A project manager in a large government agency is implementi...
Question 245: Delays from two software vendors are causing testing times t...
Question 246: During a project's execution, a previously unidentified stak...
Question 247: A project manager joins a project that is similar to one tha...
Question 248: A project is in the closure phase. The deliverables have bee...
Question 249: Enterprise Environmental Factors includes some elements such...
Question 250: After receiving the hardware components from a vendor that w...
Question 251: A project manager is conducting a protect benefits analysis ...
Question 252: A project manager invites stakeholders to a gate review meet...
Question 253: A project manager plans the agenda for a kick-off meeting As...
Question 254: A probability and impact matrix is useful for:...
Question 255: An experienced project manager with a technical background h...
Question 256: A project's core team was reassigned to a partially complete...
Question 257: While reviewing the business case for a newly assigned proje...
Question 258: What basic quality tool should a project manager use to unde...
Question 259: A team member realizes that a technical update will improve ...
Question 260: Which conflict resolution technique is most likely to result...
Question 261: A project is completed and the product design packaging is d...
Question 262: You are managing a large construction project. Two of your t...
Question 263: During a status meeting, a stakeholder requests a new requir...
Question 264: A project manager wants to minimize the risks for a multinat...
Question 265: In which process groups are the project deliverables reviewe...
Question 266: A start-up company's project team completes its first produc...
Question 267: An experienced project manager is preparing a kick-off meeti...
Question 268: A project manager is preparing the project management plan f...
Question 269: A project requires specialized technical expertise from the ...
Question 270: A company has traditionally used waterfall methodologies for...
Question 271: A car manufacturing company wants to develop an unmanned car...
Question 272: A new project manager on a project with a very tight budget ...
Question 273: A project's earned value (EV) report indicates that can acti...
Question 274: A project is delivered that meets the approved business requ...
Question 275: A project manager is performing a set of processes in the In...
Question 276: During the initiation phase of a healthcare IT project the p...
Question 277: A company has been awarded a project to develop products for...
Question 278: A project team member delivered one of the main deliverables...
Question 279: A change has occurred in your project. You've documented the...
Question 280: A client adds a new feature and requests a budget update the...
Question 281: A project's budgeted value of work completed is less than th...
Question 282: A software system was developed and implemented in a project...
Question 283: In a project with a multigenerational team, some resources a...
Question 284: An issue will cause the project team to miss a critical mile...
Question 285: : A design team discovers that the work breakdown structure ...
Question 286: You are a Project Manager working on a project to create hig...
Question 287: It was found that the developers are reluctant to perform ch...
Question 288: An IT department's deliverable is two weeks late If the deli...
Question 289: A division manager wants to transfer a key team member off o...
Question 290: A product development manager, who is unsure of an initial p...
Question 291: A project manager, working on a project with members in diff...
Question 292: While working on a project, the project team realizes that r...
Question 293: The project manager of a technical team receives a complaint...
Question 294: To begin transitioning the final deliverables to the client,...
Question 295: As a project progresses the project manager notices that wee...
Question 296: A project manager developed the scope management plan for a ...
Question 297: A project manager is developing a project risk register. Wha...
Question 298: A project manager presents the project scope and durables to...
Question 299: A project manager takes over a project after its project man...
Question 300: A new project manager joins a company to work on a new. firs...
Question 301: An impact assessment reveals that a deliverable could delaye...
Question 302: A protect manager leaves the company and a new project manag...
Question 303: You are a project manager managing a global project. You hav...
Question 304: A project manager begins a project to develop a network of w...
Question 305: A project manager is working on a product-line project with ...
Question 306: A new execute asks the project manager to share sensitive pr...
Question 307: You work as a project manager for your company. You want to ...
Question 308: You are a project manager working on a software development ...
Question 309: A project manager discusses a project's status with the cust...
Question 310: After approval of user acceptance testing for a project, all...
Question 311: The preferred method to settle claims and disputes in the pr...
Question 312: A project has been in execution for three months. A new team...
Question 313: A project manager is working in a hybrid environment using b...
Question 314: During project execution, a project team develops a new resp...
Question 315: A senior manager asks a loam member for a quick update on th...
Question 316: A project manager is creating a program evaluation and revie...
Question 317: A project manager publishes a survey to assess stakeholder s...
Question 318: After receiving the approved project charter, a stakeholder ...
Question 319: An e-commerce web page is being developed externally per a t...
Question 320: For a highly regulated financial-industry project, the team ...
Question 321: One of the key stakeholders for a project sent an email with...
Question 322: Midway through a project's execution phase, the client asks ...
Question 323: A demanding project stakeholder insists that an additional f...
Question 324: During a project's execution phase, project members have fre...
Question 325: During scope verification meetings, an end user often reject...
Question 326: If an agile approach is used, which of the following techniq...
Question 327: An identified project risk occurs, and the project manager i...
Question 328: Halfway through a project, the project manager determines th...
Question 329: A company is about to fund a new project to develop a produc...
Question 330: A vendor submits a high-level project schedule for a three-y...
Question 331: During an audit, a team member complains about the quality o...
Question 332: A company has recurring quality issues with one of its sole-...
Question 333: During a stakeholder meeting, the project manager receives r...
Question 334: A project manager has just been informed that it is extremel...
Question 335: During the planning stage of a project, a project manager id...
Question 336: A project manager is assigned to an ongoing project and rece...