A new project manager joins a project in its execution phase that is behind schedule and over budget. A brief first analysis reveals that this is due to a dissatisfied stakeholder. After further review of project documentation, the manager determines that this stakeholders has high power and high interest in the project. The project manager decides to meet with the stakeholder to review the stakeholder's expectations. After the meeting, what should the project manager do first?