While sequencing project activities the team defines that: * Activity A has a duration of three weeks. * Activity C, with a duration of four weeks, will start first. * Activity B, with a duration of two weeks, will start with a lead time of one week upon completion of activity B. * Activity E, with a duration of five weeks, will start after the completion of activity C. * Activity F, with a duration of three weeks, will have a start-to-dependency with activity E, with lag time of three weeks. What is the project's shortest possible duration?