A project manager has finished creating a detailed schedule of a 20-month project, which includes a two-month buffer. The project manager sends the schedule to the external client for approval, but the client does not approve it. stating that the project should only take 18 months, including the two-month buffer. In order to resolve this conflict, what should the project manager do first?