Valid PMP-CN Dumps shared by ExamDiscuss.com for Helping Passing PMP-CN Exam! ExamDiscuss.com now offer the newest PMP-CN exam dumps, the ExamDiscuss.com PMP-CN exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP-CN dumps with Test Engine here:
設施擴建工程正處於執行階段。有一個專案活動將所有新設備的電源連接到現有設施 A 點,這需要相當長的電纜。施工隊發現可以把電源接到B點,省錢。 專案經理接下來該做什麼?
Correct Answer: A
The Project Management Professional (PMP) guidelines emphasize the importance of a cost-benefit analysis as a systemic approach to evaluate and compare the costs and benefits of different project proposals. This process is crucial when considering changes that can impact project costs and benefits. It involves determining all direct and indirect cost estimates, defining and calculating all tangible and intangible benefits, and using an appropriate Cost Benefit Analysis (CBA) algorithm to analyze the cost and benefit streams12. Additionally, the PMBOK Guide's change management process outlines the need for an impact analysis of change requests, which is a key component of the cost-benefit analysis, before presenting the change to the Change Control Board (CCB)3. References: * Cost-Benefit Analysis: A Quick Guide with Examples and Templates1. * Benefit-Cost Ratio PMP Exam Guide2. * PMBOK Guide Change Management Process For PMP Exam3.