專案經理正在使用混合方法來遵守監管要求。規劃和收尾階段將使用預測方法,執行階段將使用迭代方法。在第二次衝刺審查期間,專案發起人要求更改某些產品積壓專案的優先順序。
身為僕人式領導,專案經理該做什麼?
Correct Answer: B
A project manager who uses a hybrid approach should be able to adapt to changes in the project environment and support the agile principles of delivering value to the customer and embracing change. As a servant leader, the project manager should empower the product owner to make decisions about the product backlog and prioritize the items that deliver the most value. Asking the sponsor to submit a change request to the CCB, accepting the request without consulting the product owner, or reviewing the impact of the change on the schedule management plan baseline are not appropriate actions for a project manager who uses a hybrid approach, as they imply a rigid and bureaucratic process that does not align with the agile mindset. References:
* PMBOK Guide, 6th edition, page 18
* Agile Practice Guide, page 13
* PMI-PBA Exam Content Outline, page 9
* [PMI-PBA Handbook], page 10