專案經理正在領導一個有嚴格期限的敏捷軟體開發專案 客戶抱怨最後的部署不符合驗收標準 開發團隊負責人認為部署符合所有規範並提供了客戶規範的證據 專案應該做什麼經理做什麼?
Correct Answer: B
In an agile software development project, the project manager should focus on collaboration and communication to resolve issues. When a client complains that the last deployment did not meet the acceptance criteria, it's crucial to review the requirements traceability matrix. This matrix is a document that links requirements throughout the validation process, helping to ensure that all requirements defined for a system are tested in the test protocols. By reviewing this matrix with the team lead and the client, the project manager can identify any discrepancies between the client's expectations and the team's understanding of the specifications. This collaborative approach can help to resolve the issue effectively. References: Project Management Professional (PMP) Reference Materials, Professional in Business Analysis Reference Materials