一名專案經理正在領導一個跨組織項目,該專案正在更換一個平台,該平台上建立了 15 個業務部門使用的各種解決方案。該專案是大型工作計劃的一部分,部分資源與各業務部門發起的計劃以外的其他專案共享。
專案經理應該先諮詢哪些利害關係人來管理相互依賴?
Correct Answer: D
Managing interdependencies in a cross-organizational project, especially one that affects multiple business units and shares resources with other projects, requires a coordinated approach. The PMBOK Guide highlights the importance of identifying and engaging stakeholders who can influence the project's outcomes1. In this scenario, program managers are typically responsible for overseeing the program's overall direction and managing dependencies across projects within the program2. Consulting with program managers first can provide a comprehensive view of the program's objectives, resources, and constraints, which is crucial for effectively managing interdependencies. References: Stakeholder Management - Project Management Institute; Project Stakeholder Management According to the PMBOK12.