一個組織正在向敏捷交付過渡,並且已經組建了一個新團隊。專案進展不順利是因為團隊速度的變化非常大,每個衝刺交付的成果都低於承諾的成果。該專案已任命一位具有強大技術背景的新專案負責人。
專案負責人該做什麼?
Correct Answer: D
In agile delivery, it's important to reflect on processes and make adjustments as needed. The project lead should facilitate a discussion during the retrospective to explore different estimation methods that could improve accuracy and consistency. This is a key opportunity for the team to analyze the causes of the high variation in velocity and less-than-committed delivery, and to collaboratively find solutions that leverage the team's collective expertise.
References: This guidance is aligned with agile principles, which advocate for continuous improvement and adapting the process to work effectively for the team. The retrospective is the ideal time for such discussions, as it is a dedicated moment for reflection and planning improvements for the next sprint.