Correct Answer: A
A hybrid project is a project that combines predictive and adaptive approaches. In such a project, the project manager should engage the project team in implementing and improving key aspects of the standup meetings, such as setting clear goals, keeping time limits, and providing feedback. This is a way to foster collaboration, communication, and alignment among the team members, regardless of their location or methodology. Asking the product owner to remove team members, sending a daily retrospective report, or including a daily brainstorming session are not effective ways to improve the situation with the project team, as they do not address the root cause of the problem, which is the lack of value and understanding of the standup meetings. References: [PMI Agile Practice Guide], page 14; How to Run Effective Stand-Up Meetings [2024]
* Asana, section 6 steps to more effective stand-up meetings; Hybrid meetings guide - Microsoft Research, section 1. Set clear goals for the meeting.