Correct Answer: B
According to the PMBOK Guide, 6th edition, section 4.7, one of the main outputs of the close project or phase process is the final product, service, or result transition. This involves transferring the ownership and responsibility of the project deliverables to the customer or sponsor, and obtaining their formal acceptance and sign-off. The project manager should ensure that the project scope and quality criteria are met, and that the deliverables are aligned with the project objectives and stakeholder expectations. The other options are not appropriate for the end of the project, as they are either part of the planning or monitoring and controlling processes, and do not involve the client's verification and acceptance. References: PMBOK Guide, 6th edition, section 4.7; PMP Practice Exam, question 86.