專案經理正在與三個虛擬團隊一起處理一個專案。 A 團隊與 B 和 C 團隊處於不同的時區。資訊到達團隊 A 較晚或有時會遺失,並且 B 團隊和 C 團隊優先考慮彼此的問題而不是 A 團隊。 專案經理應該做哪兩件事來幫助團隊更好地協作? (選兩項)
Correct Answer: A,C
To enhance collaboration among virtual teams, especially when one team feels isolated due to time zone differences, the project manager should consider implementing strategies that promote inclusive communication and regular engagement. Option A, scheduling weekly progress meetings with all three teams, ensures that each team has the opportunity to be heard and to participate actively in the project's progress. This approach fosters a sense of unity and allows for synchronous communication, where immediate feedback can be provided and all teams are updated simultaneously12. Option C, updating the communications management plan, is crucial for addressing the current issues faced by Team A. By encouraging all teams to review the communications plan promptly and proactively, the project manager can ensure that information dissemination is timely and no team is left out of the loop. This step also allows for the identification of any gaps in the current communication strategy and the implementation of improvements to facilitate better collaboration12. While the other options may have their merits, they are not as immediately impactful as A and C for addressing the current challenges of feeling left out and information delays experienced by Team A. References: * Best practices for managing and developing virtual project teams, which highlight the importance of regular meetings and effective communication plans1. * Leading virtual project teams, which provide insights into the dos and don'ts of virtual team management, emphasizing the need for inclusive and regular communication2.