一個混合專案剛剛部署,專案經理正在計劃透過經驗教訓研討會來結束專案。一位關鍵利害關係人告訴專案經理,讓 Scrum 團隊參加研討會是浪費時間,因為專案已成功交付。
專案經理該做什麼?
Correct Answer: D
The importance of involving the Scrum team in lessons learned workshops, even after a successful project delivery, is emphasized in project management methodologies. Lessons learned are a vital part of project closure, as they provide documented information that reflects both the positive and negative experiences of a project. They are crucial for the team, the organization, and for the success of future projects. The Scrum team's involvement ensures that insights and retrospectives are comprehensive, covering all aspects of the project's execution123. Moreover, in Scrum, every sprint is considered a project, and the framework is designed to maximize value and control risk through continuous feedback, which includes lessons learned from each sprint4.
References: = Lessons learned are an integral part of project management excellence and are strongly encouraged by the project manager from the beginning of the project1. The Project Management Body of Knowledge (PMBOK) also highlights the significance of project closure and lessons learned review as they help finalize project deliverables, evaluate project performance, document project outcomes, and capture project learnings3. Additionally, Scrum.org emphasizes that Scrum does not include "closing a project" but rather retiring a product, and the continuous improvement and learning from each sprint are fundamental to the Scrum process4.