專案經理正在從事一個軟體開發專案。專案經理和專案團隊識別了專案風險。隨著專案的進展,其中一項風險出現,專案經理參考風險管理計畫來決定如何管理風險。一旦選擇並實施了風險管理策略,風險就關閉了。
專案經理在什麼時候將風險從風險登記冊移至問題日誌?
Correct Answer: B
The transition of a risk from the risk register to the issue log occurs when a risk materializes, meaning it has happened. In project management, risks are potential problems that may or may not happen, and they are documented in the risk register. When a risk actually occurs, it becomes an issue and is then moved to the issue log for tracking and resolution. This is consistent with the PMBOK guide's definition and treatment of risks and issues.
References: = Project Management Institute (PMI) resources, including the PMBOK guide and PMP examination content outline, which detail the risk management process and the use of the risk register and issue log1234.