在專案實施過程中,一名新的專案經理被分配到該專案。專案經理意識到新的稅務政策會造成成本超支 25% 的風險 專案經理更新了風險登記冊並保持專案正常運作 CEO 宣布專案可以取消,因為可接受的成本超支僅為20%。專案經理非常驚訝,因為這是新資訊。
專案經理應該怎麼做才能避免這種情況?
Correct Answer: B
The project manager should have implemented the communications management plan properly to avoid this situation. The communications management plan is a component of the project management plan that defines how the project information will be communicated to the stakeholders, such as the frequency, format, content, and methods of communication. The project manager should have followed the communications management plan to inform the CEO and other relevant stakeholders about the new tax policies and their impact on the project cost, as well as the updated risk register and the proposed risk responses. This would have enabled the project manager to manage the expectations of the stakeholders, address their concerns, and seek their support and approval for the project continuation. The project manager should have also used effective communication skills, such as active listening, feedback, and conflict resolution, to ensure a clear and mutual understanding of the project status and issues. By communicating the project information properly, the project manager could have avoided the surprise and potential cancellation of the project by the CEO. References: PMBOK Guide,
6th edition, section 10.1.3.1, page 377, PMP Exam Prep, 10th edition, page 368