營運總監向 CEO 抱怨專案第一次衝刺的結果 營運部門由於績效指標不佳而無法支援新產品 專案團隊協調員向專案團隊尋求回饋,並被告知績效資訊已提交可在應用程式伺服器日誌中找到該投訴應如何解決?
Correct Answer: D
The best way to address the complaint is to involve the operations director or a representative from the operations team in the agile process. By inviting them to the validation and sprint meetings, they can provide feedback, clarify requirements, and validate the product increments. This will help to ensure that the product meets the performance indicators and the expectations of the operations department. It will also foster collaboration and transparency among the stakeholders and the project team. References: * What is a Sprint Review? | Scrum.org * What Is a Sprint Review? Goals and Tips for Running This Scrum Event * What is a sprint review? 3 steps to better sprint reviews - Atlassian * What is Stakeholder Management? - ProjectManager * What is Stakeholder Management? | A Step-by-Step Guide - Creately