Correct Answer: B
The project manager should use the monitor and control project work process to track, review, and report the progress and performance of the project. This process involves collecting, measuring, and analyzing project data to identify variances from the baseline and take corrective actions if needed. One of the tools and techniques for this process is data analysis, which includes root cause analysis. Root cause analysis is a technique to identify the underlying factors that cause a problem or a deviation from the expected outcome. By conducting root cause analysis, the project manager can understand why some team members are not completing their tasks on time and address the issues accordingly. This could involve providing feedback, coaching, training, or other support to the team members. Communicating the delivery dates more frequently (option A) may not be effective if the team members are facing other challenges or obstacles that prevent them from meeting the deadlines. Mentoring the team members to work in a remote environment (option C) may be helpful, but it is not the best option to resolve the current situation. The project manager should first identify the specific causes of the delays and then provide the appropriate guidance or assistance. Talking to the resource managers and requesting additional resources (option D) may not be feasible or necessary, as it may increase the project cost and complexity. Moreover, adding more resources may not solve the problem if the existing team members are not performing well or have other issues that affect their productivity. References:
(Professional in Business Analysis Reference Materials source and documents)
* PMBOK Guide, 6th edition, pages 119-120, 4.4 Monitor and Control Project Work
* PMI, PMP Exam Content Outline, 2021, page 9, Domain II: Process, Task 7: Monitor project artifacts and resolve any deviations from the project management plan
* PMP Practice Questions #60 - iZenBridge