專案經理正在為具有嚴格定義要求的政府機構領導一個採用預測方法的專案。在專案中期,發起人要求包含一個重要的新功能。這個功能不在最初的計畫中,也不是計畫過程的一部分,專案經理該做什麼?
Correct Answer: D
According to the Project Management Body of Knowledge (PMBOK) guide, when a significant change is requested that was not part of the original plan, the project manager should first analyze the impact of this change on the project's scope, schedule, cost, and resources. This analysis should then be presented to the senior manager or project sponsor, who can make an informed decision about whether to proceed with the change.
This approach ensures that the implications of the change are fully understood before any action is taken, and it allows the project's stakeholders to make decisions based on the most accurate and up-to-date information.
This is a key aspect of effective change management in project management. References: PMBOK Guide, 6th Edition, Section 4.5: Perform Integrated Change Control.