在具有兩個團隊(A 和 B)的專案的第二次迭代期間,專案經理擔心團隊 A 有兩個關鍵活動必須在第四次迭代中啟動。此外,這兩項活動依賴 B 團隊尚未確定優先順序的活動。 專案經理該做什麼?
Correct Answer: B
In project management, it is crucial to manage dependencies effectively to ensure that critical activities are completed on time. The project manager should ensure that team B prioritizes the dependent activity in iteration three to align with the schedule of team A's critical activities set for iteration four1. This approach is supported by best practices in managing project dependencies and inter-team coordination, ensuring that all necessary tasks are accounted for and scheduled appropriately23. References: * PMI's Guide to the Project Management Body of Knowledge (PMBOKGuide)4. * Professional in Business Analysis Reference Materials5. * Best practices in managing project dependencies23. * Discussions on PMP exam topics related to managing dependent activities between teams1