受監管行業的組織決定從預測交付方法轉向敏捷交付方法。已經決定正在進行的專案將採用Scrum,專案經理仍然對專案結果負責。在第四次衝刺演示期間,客戶注意到某個功能不符合法規。
專案經理該做什麼?
Correct Answer: D
The project manager should ensure that the product owner collaborates with the compliance officer to review the user stories in the product backlog and ensure that they meet the regulatory requirements. This is consistent with the agile principle of satisfying the customer through early and continuous delivery of valuable software.
The project manager should also monitor the compliance status of the product backlog items and communicate any risks or issues to the relevant stakeholders. The project manager should not have the team consult with the compliance officer to update the DoD for the past sprint, as this would be a waste of time and resources. The project manager should not have the product owner consult with the CCB, as this would introduce unnecessary bureaucracy and delay the delivery of value. The project manager should not have the scrum master organize a weekly meeting with the compliance officer, the product owner, and the project team, as this would reduce the autonomy and self-organization of the team. References:
* PMP Exam Content Outline (2021), Domain II: Process, Task 2: Execute project with the urgency required to deliver business value, p. 101
* A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, Chapter 5:
Project Scope Management, Section 5.4.2.1: Product Backlog, p. 1542
* Agile Practice Guide, First Edition, Chapter 2: Life Cycle Selection, Section 2.2.1: Scrum, p. 213
* Professional in Business Analysis (PBA) Examination Content Outline (2018), Domain III: Analysis, Task 1: Elicit Requirements, p. 14