To ensure that the project acceptance criteria are met for all project deliverables, the project manager should include the expectations and needs of project stakeholders in the creation of the project acceptance criteria. This aligns with the best practices in project management, which emphasize the importance of understanding and incorporating stakeholder requirements to achieve project success. By doing so, the project manager can ensure that the deliverables will meet the agreed-upon standards and satisfy stakeholder needs, which is crucial for the acceptance of the project outcomes. References: * Project Management Institute. (2024). A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition. * Project Management Institute. (2024). Project Management Professional (PMP)Certification Handbook. * KnowledgeHut. (2024). Project Management Acceptance Criteria with Examples. * ProjectManagers.Org. (2024). Project Acceptance Criteria * The Definitive Guide.