When a project team is demotivated due to a framework that is not compatible with agile delivery, the project lead should ask the PMO to review the framework. This is because the PMO is responsible for defining and maintaining project management standards and practices within an organization. A review can help identify the specific areas where the current framework is lacking and how it can be adapted to support agile methodologies. This aligns with the PMBOK guide's principles of tailoring project management practices to meet the unique needs of each project1. References: * PMBOKGuide - Sixth Edition * Agile Practice Guide2 * Disciplined Agile and PMBoK Guide 7th Edition3