一家公司正在領導一個使用敏捷方法開發新產品的專案。與供應商簽訂合同,根據強制性範圍、穩定的要求和固定價格合同,為其中一項產品功能提供解決方案。在與供應商的會議中,專案經理獲悉,該公司的業務分析師還要求供應商添加另一個功能的解決方案作為其可交付成果的一部分。
專案經理該做什麼?
Correct Answer: C
According to the PMBOK Guide, 6th edition, section 12.2.2.4, the project manager should use procurement documentation to define and manage the contractual relationships with the suppliers. Procurement documentation includes the contract, the statement of work, the procurement management plan, and the source selection criteria. The project manager should ensure that the project team, including the business analyst, is aware of the terms and conditions of the contract and the scope of work that the supplier is expected to deliver.
Any changes or additions to the scope should be formally requested and approved through the change control process, as described in section 4.6. The PMI-PBA Guide, section 6.3.3.1, also supports this approach, as it states that the business analyst should follow the change management plan and the requirements management plan to manage changes to the requirements and to communicate them to the relevant stakeholders, including the suppliers. References:
* PMBOK Guide, 6th edition, section 12.2.2.4 and 4.6
* PMI-PBA Guide, section 6.3.3.1
According to the PMBOK Guide, 6th edition, section 12.2.2.4, the project manager should use procurement documentation to define and manage the contractual relationships with the suppliers. Procurement documentation includes the contract, the statement of work, the procurement management plan, and the source selection criteria. The project manager should ensure that the project team, including the business analyst, is aware of the terms and conditions of the contract and the scope of work that the supplier is expected to deliver.
Any changes or additions to the scope should be formally requested and approved through the change control process, as described in section 4.6. The PMI-PBA Guide, section 6.3.3.1, also supports this approach, as it states that the business analyst should follow the change management plan and the requirements management plan to manage changes to the requirements and to communicate them to the relevant stakeholders, including the suppliers. References:
* PMBOK Guide, 6th edition, section 12.2.2.4 and 4.6
* PMI-PBA Guide, section 6.3.3.1