在專案管理計劃批准會議上,專案經理意識到簡報中包含太多細節,以至於許多利害關係人沒有積極參與流程。利害關係人在沒有進行實質思考的情況下就同意了範圍、目標和時間表。
專案經理應該如何進行?
Correct Answer: B
Reasoning: According to the PMBOK Guide, one of the tools and techniques for the Develop Project Management Plan process is expert judgment, which involves seeking the opinions and advice of knowledgeable and experienced individuals or groups. The project manager should ensure that the stakeholders are adequately informed and engaged in the project management plan approval process, and that they understand the implications and assumptions of the plan. The other options, such as stopping the meeting, getting approval without clarification, or obtaining approval as fast as possible, may not address the root cause of the problem, which is the lack of stakeholder involvement and commitment. Therefore, option B is the most likely answer to the question12 References:
3: PMBOK Guide, 6th edition, page 89 1: Top 60+ PMP Exam Questions and Answers for 2024 - KnowledgeHut 2: PMI PMP Quiz:111 Topic:2 Questions:551-555 - buddy4exam.com